Un/Loading Bay (South)
Anomalies:
The following anomalies were observed during the site visit:
-
Missing the whole ridge cap.
-
Corrosion of all steel elements (holes in the roof).
-
Gutters in degrading condition
Anomalies to address for the rehabilitation:
The rehabilitation will focus on the gutters and the missing ridge cap. The roof structure and roof sheets are not a priority at the moment and will be replaced gradually at a later stage.

Proceedings:
-
A contractor must be appointed to supply and install the ridge cap.
-
A Consultant must design new gutters to replace the existing gutters.
Recommendations:
Although a new roof structure is not urgent, it can be designed by the Consultant and reserved for when the time is appropriate to replace the existing one.