Finished Goods Warehouse
Anomalies:
The following anomalies were observed during the site visit:
-
Corrosion of the roof sheets.
-
Damaged concrete beam and cracked wall.
-
The roof between the empty bottles warehouse and the logistics meeting room shows signs of corrosion and has a portion of the roof missing, leaving an open space subject to all weather conditions.
Anomalies to address for the rehabilitation:
All anomalies listed above will be addressed as part of the rehabilitation.

Proceedings:
-
The entire roof should be replaced. A Consultant, structural engineer should design a new roof structure able to withstand the winds of a cyclone.
Recommendations:
It is recommended that the damaged beam and the wall inside that frame are demolished, leaving an open span.